What do general contractors check when they prequalify a subcontractor?

Subcontractor prequalification is the questionnaire a general contractor or public owner uses to score your safety record, insurance, bonding capacity, financial strength, licensing, and past projects before it will accept your bid. Most GCs require it once a year or per project, and the standard forms ask for three years of OSHA 300 and 300A logs, your experience modification rate (EMR) on carrier letterhead, a current certificate of insurance, a surety letter, and CPA-prepared financial statements. A firm with no EMR or no bonding letter is not shut out, but several forms score it at a default EMR of 1.00 or cap the prequalified contract amount.

Key facts

The numbers.

ItemValueSource
EMR baseline1.00 = expected losses for your class and size

Below 1.00 lowers your workers' comp premium; above 1.00 raises it. Computed from three years of losses, excluding the most recent policy year.

Source ↗
EMR cutoff on a public-owner form1.00 or less to prequalify

A California State University subcontractor questionnaire, for firms with fewer than ten employees.

Source ↗
EMR letter ageEffective date within 12 months, on carrier letterhead

The South Carolina DOT will not process an application without it or a carrier letter explaining why no EMR exists.

Source ↗
TRIR formula(recordable cases x 200,000) / hours worked

200,000 is the hours 100 employees work in a year at 40 hours a week for 50 weeks.

Source ↗
DART formula((column H + column I cases) x 200,000) / hours worked

Column H is days away from work; column I is job transfer or restriction, both from the 300A.

Source ↗
2024 construction benchmarkTRIR 2.2, DART 1.3 per 100 full-time workers

Specialty trade contractors (NAICS 238): 2.3 and 1.4.

Source ↗
Safety lookback3 years of OSHA 300 and 300A logs

Firms exempt from OSHA recordkeeping are still asked for equivalent data.

Source ↗
Prequal cap without a bonding letter$250,000

One national GC's manual; CPA-prepared financial statements are required to prequalify above it.

Source ↗

The nine categories on a subcontractor prequalification form

A subcontractor prequalification form is how a general contractor or public owner decides whether to let you bid, and for how much. The industry-standard form, ConsensusDocs 221, collects nine categories: project experience, current capacity and backlog, business structure, bonding and insurance, key personnel, references, financial information, licensing and compliance, and safety record including the experience modification rate (EMR). The AIA's A305-2020 qualification statement covers the same ground as a sworn, notarized statement with exhibits.

Real GC forms follow that skeleton and are signed under oath. Most state that a misrepresentation is grounds for disqualification, so every number should match a document you can produce.


Your experience modification rate (EMR) and the 1.00 line

Your EMR is a factor your workers' compensation rating bureau (NCCI in Missouri and most states) calculates from your own claims history compared with businesses of similar class and size. A mod of 1.00 means your losses match what is expected; below 1.00 lowers your premium and above 1.00 raises it. The experience period is three years, excluding the most recent policy year, so the number lags.

Owners use it as a cutoff. A California State University subcontractor questionnaire requires small firms to have an EMR of 1.00 or less to prequalify, and a national GC's manual enters 1.00 for firms not eligible for one. Owners want the figure on your carrier's letterhead with an effective date within 12 months; the South Carolina DOT will not process an application without it. If you are too new or too small to have a mod, get a carrier letter saying so. OSHA itself cautions:

Care should be taken in using EMRs, because some are workplace-specific, while others are employer-specific and involve multiple worksites. This makes direct comparisons of employers' EMRs difficult.

TRIR and DART: the two rates computed from your 300A

The total recordable incident rate (TRIR) and the days away, restricted, or transferred (DART) rate come straight off your OSHA 300A summary. OSHA's formula:

(Number of injuries and illnesses X 200,000) / Employee hours worked = Incidence rate.

The 200,000 is the hours 100 employees work in a year. TRIR counts every case on the log (columns H, I, and J of the 300A). DART counts only the column H and column I cases: days away, plus restricted or transferred. Hours worked exclude vacation and sick leave. The 2024 Bureau of Labor Statistics benchmark for construction is a TRIR of 2.2 and a DART rate of 1.3 per 100 full-time workers; specialty trade contractors run 2.3 and 1.4. Forms ask for three years of both rates with the 300 and 300A logs. One injury swings a small crew's rate hard; OSHA says pooling three years of cases and hours in the formula is legitimate.


The certificate of insurance and the three endorsements GCs want

A certificate of insurance is the one-page ACORD 25 form your agent issues showing your general liability, auto, workers' compensation, and umbrella policies with limits and dates. It is evidence, not coverage: a certificate confers no rights on the GC. Protection comes from endorsements on your policies, and three are standard asks: additional insured status for the GC, including completed operations; primary and non-contributory wording, so your policy pays first; and a waiver of subrogation, so your insurer will not chase the GC.

The failure list on one GC's form shows what its insurance spec contains: general liability above $1 million per occurrence through an umbrella, a per-project aggregate, additional insured coverage including completed operations with primary wording, and pollution or mold coverage. Have your agent attach the endorsement forms by number.


Bonding capacity and the surety letter

The Federal Acquisition Regulation, 48 CFR 28.001, defines the two bonds a GC cares about:

A payment bond assures payments as required by law to all persons supplying labor or material in the prosecution of the work provided for in the contract.
A performance bond secures performance and fulfillment of the contractor's obligations under the contract.

A prequalification form asks whether you are bondable, who your surety is, your single-project and aggregate capacity, your rate, and how much is under bond. A bonding letter from your surety dated within the last year answers all of it. One national GC prequalifies a sub with no bond letter at a $250,000 ceiling and requires CPA-prepared financial statements to go higher. Surety underwriters judge character, capacity, and capital, and treat the bond as credit you repay, which is why financial statements are the gate. If a commercial surety will not write you, the SBA Surety Bond Guarantee program backs bonds on contracts up to $9 million for a fee of 0.6% of the contract price on performance and payment bonds.


Licensing in Missouri and Illinois, and the three documents that expire

In the prequal's compliance section, license means whatever the city or trade requires where the job sits. Missouri issues no statewide general contractor license; its only statewide contractor license is electrical, under RSMo 324.900. Illinois issues none either: the state licenses roofing and plumbing contractors, and Chicago licenses general contractors in five classes with general liability minimums from $1 million to $5 million per occurrence; subs on a Chicago job work under the GC's license.

Prequalification expires. Renew it with the three dated documents: the EMR letter, the certificate of insurance, and financial statements dated within six months.

FAQ

Common follow-ups.

What if my company does not have an EMR?

Ask your workers' comp carrier or agent for a letter on letterhead stating that no EMR has been issued and giving the policy effective date. Public owners such as the South Carolina DOT require that letter, and at least one national GC scores a firm without an EMR at 1.00.

Can I prequalify without a surety bond?

Often yes, at a lower limit. One national GC prequalifies a sub with no bonding letter at $250,000 and raises the limit with a surety letter and financial statements. If a commercial surety turns you down, the SBA Surety Bond Guarantee program backs bonds on contracts up to $9 million.

How many years of OSHA logs do I need to keep ready?

Three. The public-university, private-university, and GC forms reviewed all ask for OSHA 300 and 300A logs for the previous three full calendar years, plus TRIR, DART, EMR, and citations for the same years.

Does a certificate of insurance give the GC coverage under my policy?

No. The ACORD 25 certificate is a snapshot of your coverage on its issue date and confers no rights. Additional insured status, primary and non-contributory treatment, and waiver of subrogation exist only if the endorsement is attached to your policy.

Do I need a state contractor license in Missouri or Illinois?

Neither state licenses general contractors. Missouri licenses electrical contractors statewide; Illinois licenses roofing and plumbing contractors, and Chicago licenses general contractors by project value. Licensing otherwise sits with the city or county where the job is.

How often do I have to re-prequalify?

Prequalification expires and is renewed on the GC's schedule, commonly yearly. Expect to resubmit the three dated documents: an EMR letter within 12 months, a current certificate of insurance, and financial statements dated within six months.

Sources

Where the numbers come from.

  1. ConsensusDocs 221, Subcontractor Prequalification Statement, ConsensusDocs. Retrieved .
  2. AIA A305-2020, Contractor's Qualification Statement (summary), AIA Contract Documents. Retrieved .
  3. CSU Subcontractor Technical Prequalification Questionnaire (Cal Poly Humboldt RFP PW25-1, Appendix B-1), California State University. Retrieved .
  4. Novak Construction, Subcontractor Prequalification Questionnaire (2023), Novak Construction Company. Retrieved .
  5. Howard University, Subcontractor Health and Safety Evaluation Questionnaire, Howard University. Retrieved .
  6. Sundt Construction, Prequalification Manual for Subcontractors (v10.28.24), Sundt Construction. Retrieved .
  7. SCDOT Prime Contractor Prequalification Application, Short Form CA-1S, South Carolina DOT. Retrieved .
  8. OSHA Directive CSP 03-02-001, OSHA Strategic Partnerships, OSHA. Public domain (US federal). Retrieved .
  9. NCCI, ABCs of Experience Rating, NCCI. Retrieved .
  10. Missouri Department of Commerce and Insurance, National Council on Compensation Insurance, Missouri DCI. Retrieved .
  11. OSHA Standard Interpretation, 2016-08-23, incident rate formula, OSHA. Public domain (US federal). Retrieved .
  12. OSHA Forms 300, 300A, 301 package, incidence rate worksheet, OSHA. Public domain (US federal). Retrieved .
  13. BLS, How to compute a firm's incidence rate, Bureau of Labor Statistics. Public domain (US federal). Retrieved .
  14. BLS Table 1, Incidence rates of nonfatal occupational injuries and illnesses by industry, 2024, Bureau of Labor Statistics. Public domain (US federal). Retrieved .
  15. Insureon, What is an ACORD 25 Certificate of Liability Insurance?, Insureon. Retrieved .
  16. Independent Agent, ACORD 25: Including Additional Insured Status and Waiver of Subrogation, Independent Agent magazine. Retrieved .
  17. FAR 28.001, Definitions (48 CFR), GSA, acquisition.gov. Public domain (US federal). Retrieved .
  18. Merchants Bonding, The Three Cs of Surety Bonding, Merchants Bonding Company. Retrieved .
  19. SBA Surety Bond Guarantee program, SBA. Public domain (US federal). Retrieved .
  20. Missouri Division of Professional Registration, professions list, State of Missouri. Retrieved .
  21. RSMo 324.900, electrical contractor definitions, Missouri Revisor of Statutes. Retrieved .
  22. City of Chicago, General Contractor License, City of Chicago. Retrieved .
  23. IDFPR, Roofing contractor license application, Illinois Department of Financial and Professional Regulation. Retrieved .
  24. IDPH, Plumbing licensing, Illinois Department of Public Health. Retrieved .

Reviewed against these sources on . Rules change; confirm the current text at the source before you act on a deadline or a dollar figure.

Capability Statement · $39 · Instant

Get the one-pager GCs ask for

The one-pager GCs actually ask for. Trades, bonding, EMR, past work, contacts. Formatted so it gets read.

Get notified →